Project Scheduling & Delay Recovery - field note 077
by Arjun Patel
#Monsoon Delay Recovery: Schedule Compression and Workforce Scaling
The 30,000‑sq ft Chennai hospital faced a 3‑month delay due to monsoon flooding. BuildFast revised the master plan on 18‑June‑2024. Schedule compression achieved 4 weeks of lost time.
Recovery actions:
- Re‑sequenced foundation work to start before rains.
- Hired a second crew to work in parallel on interior finishes.
- Introduced daily progress reviews with the client.