Project Scheduling and Delay Recovery - field note 027
#Delay Recovery Strategies for Steel Delivery Delays
The office tower in Chennai faced a 14‑day delay due to late delivery of steel from Vendor X.
We introduced a buffer of 5% in the critical path and accelerated the concrete pour to compensate.
- Update Gantt with real‑time data.
- Prioritize tasks with high impact.
- Negotiate faster shipping with Vendor X.
- Allocate overtime for key trades.
Result: Project back‑on‑track with only 2 days of additional cost.