Project scheduling and delay recovery - field note 005
by Ananya Joshi
The 12-month municipal water treatment plant in Delhi faced a 2-month setback when monsoon rains halted excavation.
To recover, we introduced a parallel works strategy, allowing trench lining to proceed while earthworks resumed.
- Reallocate labor to high-priority tasks.
- Secure temporary drainage to protect active zones.
- Extend contractor working hours.
- Maintain open communication with the client.
The plant is now back on track, with the commissioning date shifted only 3 weeks later.