MEP coordination - field note 018

by Kavya Jain

During the HVAC fit‑out for the 5‑storey museum in Jaipur, I noticed a clash between the chilled water riser and the structural beam. By collaborating with the MEP vendor, we rerouted the pipe through a 20 mm clearance and updated the BIM model, avoiding a 12 % cost increase. Lesson: early clash detection saves time.

  • Conduct a joint BIM review every fortnight.
  • Use clash‑report export to generate action items.
  • Verify clearances on the site before installation.
  • Update the change‑order log in the project management system.