MEP coordination - field note 058

by Vivaan Yadav

#BIM-Driven Zero-Clash MEP Coordination

During the 6‑storey hotel in Bangalore, we integrated MEP systems early using a shared BIM model. This prevented the typical 15% clash rate seen in similar projects.

  • Conducted weekly interdisciplinary coordination meetings.
  • Used clash‑free routing for HVAC ducts and electrical conduits.
  • Implemented a real‑time issue tracker for MEP conflicts.
  • Trained installation crews on updated routing plans.

Zero Clash Report was achieved, accelerating commissioning by 2 weeks.