#Site Logistics Optimization: Centralized Yard Layout and GPS Tracking Cut Fuel Use

On the Pune Industrial Complex, we re‑engineered the site yard layout to centralize all excavated material, cutting the average truck turnaround time from 15 min to 5 min.

  • Design a single loading dock; - Assign dedicated crew for material staging; - Use GPS tracking for truck routes; - Schedule haulage during off‑peak traffic.

This optimization lowered fuel consumption by 22% and helped us finish the 5000 m³ move within the 6‑week window.